After deciding on a change request's outcome, what is the project manager's next step?

Prepare for the CertMaster Project+ Exam with flashcards and multiple choice questions. Get intuitive hints and explanations to ensure you're exam-ready! Excel in your Project+ certification.

After a project manager has determined the outcome of a change request, the next critical step is to communicate the change status to relevant stakeholders. This ensures that everyone is aware of the decision made regarding the change request, whether it has been approved, denied, or deferred. Clear communication is vital for maintaining transparency and ensuring that all team members and stakeholders are aligned with the project's current direction and any adjustments that may impact their tasks or responsibilities.

By informing stakeholders about the change status, the project manager fosters understanding and cooperation, which is essential for effective project execution. It paves the way for subsequent steps, such as validating the implementation or updating project documentation, but initial communication sets the foundation for all future actions related to the change.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy