If a project manager transfers a risk to a third party, what strategy is being implemented?

Prepare for the CertMaster Project+ Exam with flashcards and multiple choice questions. Get intuitive hints and explanations to ensure you're exam-ready! Excel in your Project+ certification.

When a project manager chooses to transfer a risk to a third party, the strategy being implemented is transferring the risk. This involves shifting the responsibility of managing the risk to another entity, which can often be an insurance company or another vendor specialized in handling such risks. By doing this, the project manager reduces the potential negative impact on the project, allowing the third party to manage or absorb the consequences associated with that risk.

Transferring risks can be an effective way to protect the project’s budget and resources, as it often entails a contractual agreement where the third party assumes liability or shares responsibility. This approach allows the project team to focus on their core project objectives without being disproportionately affected by specific risks that are outside their control.

In contrast, avoiding a risk would mean taking steps to eliminate it entirely, while accepting a risk involves acknowledging its presence without active measures to address it. Mitigation strategies seek to reduce the likelihood or impact of a risk but still retain some responsibility for it. Thus, transferring the risk distinctly reallocates accountability to another party, making it a unique and strategic choice in risk management.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy