In a Work Breakdown Structure (WBS), where should high-level deliverables be placed?

Prepare for the CertMaster Project+ Exam with flashcards and multiple choice questions. Get intuitive hints and explanations to ensure you're exam-ready! Excel in your Project+ certification.

In a Work Breakdown Structure (WBS), high-level deliverables are appropriately placed at the element level. The WBS is a hierarchical decomposition of a project into manageable sections, and at the top levels, the focus is on high-level deliverables that encapsulate major project outcomes or phases.

Elements in the WBS represent these significant deliverables and are crucial for facilitating the project's understanding and management. Clearly identifying high-level deliverables helps project managers and team members see the overall structure and the scope of the project, which aids in communication, planning, and resource allocation.

As the WBS is broken down further, it moves from these high-level elements down to more detailed components, like work packages, which contain specific tasks and activities necessary to achieve the deliverables. This structured format ensures that every part of the project is accounted for and supports effective tracking and management throughout the project lifecycle.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy