What is a characteristic of a Start-to-Finish dependency?

Prepare for the CertMaster Project+ Exam with flashcards and multiple choice questions. Get intuitive hints and explanations to ensure you're exam-ready! Excel in your Project+ certification.

A Start-to-Finish dependency is a specific type of relationship in project management where one task cannot be completed until another task has started. This means that for Activity 2 to finish, it must be dependent on Activity 1 starting first.

In this type of dependency, the emphasis is on the sequence involving the start of the first activity. Here, even though Activity 1 has not yet completed, Activity 2 cannot finish until there is some progress in Activity 1. This relationship is less common than other dependency types, such as Finish-to-Start, but is beneficial in certain scenarios where the lag between tasks is crucial.

Understanding this dynamic helps project managers visualize task sequences and dependencies accurately, ensuring that project timelines reflect the necessary relationships between activities.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy