What is the result of a project manager reallocating funds from contingency reserves to cover project costs?

Prepare for the CertMaster Project+ Exam with flashcards and multiple choice questions. Get intuitive hints and explanations to ensure you're exam-ready! Excel in your Project+ certification.

When a project manager reallocates funds from contingency reserves to cover project costs, it results in a decrease in the reserve balance because those funds are being utilized for actual expenses rather than being set aside for unforeseen issues or risks in the project. The act of reallocating contingency funds does not increase the overall project estimate; instead, it affects only the allocation of existing funds.

Contingency reserves are financial buffers intended for unexpected costs that may arise during the project lifecycle. When these funds are reallocated to cover costs that are currently incurred, it indicates that the project is experiencing higher-than-anticipated expenses or risks have materialized, which necessitated the use of these reserves.

Thus, while the reserve balance decreases with this reallocation, the project’s original estimate remains unchanged because it reflects the total approved budget prior to actual expenditures. This scenario highlights the management of risk and financial planning within project management, ensuring that resources are appropriately assigned to meet project objectives.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy