Which approach can project managers take to quickly respond to escalating low-priority issues?

Prepare for the CertMaster Project+ Exam with flashcards and multiple choice questions. Get intuitive hints and explanations to ensure you're exam-ready! Excel in your Project+ certification.

The correct approach for project managers to respond quickly to escalating low-priority issues is to execute the contingency plan. This plan is designed to address potential risks and issues that may arise during a project. When a low-priority issue escalates, it indicates a need for a pre-defined method to address impacts without derailing the overall project pace or strategy.

Executing a contingency plan allows project managers to utilize established protocols efficiently, minimizing disruption and ensuring that resources can be allocated effectively to resolve the issue. By having a plan in place, the project team can react promptly instead of waiting to analyze or document the problem, which may delay resolution.

Other methods, such as conducting a root cause analysis, focus more on understanding the underlying causes of a problem. While valuable for long-term improvements, this approach is time-consuming and may not provide immediate relief for an escalating issue. Adding the issue to the tracking system is essential for documentation and follow-up but does not offer a proactive solution to the current problem at hand. Terminating the project is too drastic and not suitable for dealing with low-priority issues, as it can lead to more significant consequences and cost implications without necessity.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy