Which of the following terms refers to a group meeting where project outcomes are reviewed before final sign-off?

Prepare for the CertMaster Project+ Exam with flashcards and multiple choice questions. Get intuitive hints and explanations to ensure you're exam-ready! Excel in your Project+ certification.

The term that refers to a group meeting where project outcomes are reviewed before final sign-off is the project closure meeting. This meeting serves as a critical point in the project lifecycle, allowing stakeholders to assess whether all project objectives have been met and if the project deliverables align with the initial goals and requirements. It is an opportunity for the project team and stakeholders to discuss lessons learned, address any outstanding issues, and confirm the project’s completion status before formally closing it.

In this setting, stakeholders typically evaluate the work done, review project documentation, and ensure that all contractual obligations have been fulfilled. The closure meeting is essential for fostering communication and consensus among team members and stakeholders, making it easier to transition any remaining responsibilities or deliverables.

Other terms listed, such as budget reconciliation, project sign-off, and project closeout report, refer to different aspects of project management. Budget reconciliation deals specifically with financial elements, project sign-off pertains to formally accepting the completed work, and the project closeout report is a document summarizing project performance. While all these elements may occur during or as part of the closure phase, the project closure meeting specifically emphasizes the collaborative review of project outcomes leading up to final approvals and closure.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy